A selection of significant projects delivered by Oaksling for government, defense, and commercial clients.
Installed the complete HVAC system for the Joint Operations Center, including 3 VRV systems with a combined 16 air handlers and 3 outside air units. Project delivered on time with full commissioning and documentation.
Contracted for the complete MEP (Electrical, Plumbing, Mechanical, and HVAC) works at the new Department of State building. Scope included all mechanical, electrical, and plumbing systems from rough-in through commissioning.
Installed pedestal floating flooring for a 650 square-meter government building, raised 60cm above the concrete slab. Precision installation completed to full specification.
Completed the procurement and remote delivery of custom energy-efficient windows for National Park Service facilities in Kotzebue. The order included triple-glazed, argon-filled units, secure protective packaging, and coordinated marine and air transport to remote Alaska.
Completed barracks flooring work including furniture handling, carpet and adhesive removal, subfloor preparation, installation of approximately 12,000 square feet of vinyl composite tile, new cove base and transitions, protective finishing, and final cleanup, all while the buildings remained in use.
Contracted to assemble and distribute 13,953 pieces of furniture across Microsoft's facility. Executed with zero errors, on schedule, and with full inventory documentation.
Installed 1,000 meters of main electric cabling (185×5) at Hatzor Air Force Base, connecting an electrical substation to a critical building. High-security, precision installation with zero tolerance for error.
Complete VRF HVAC system installation including 3 systems, 16 air handlers, and 3 outside air units for a critical defense operations facility.
Procured, quality-checked, securely packaged, and delivered custom energy-efficient windows to Western Arctic Parklands facilities in a remote Alaskan environment.
Replaced barracks carpet with durable vinyl composite tile across Buildings 292 and 294, including surface preparation, cove base, transitions, finishing, and site restoration.
Completed the procurement, delivery, and installation of transformers in accordance with government specifications and required project documentation.
Supplied and installed backflow preventers in accordance with project specifications, coordinating delivery, on-site installation, and supporting documentation.
Completed the procurement, delivery, and installation of HVAC equipment, with detailed quality checks, secure transportation, and documentation aligned to federal requirements.
Contracted to design, repair, and maintain the HVAC and smoke extraction system for the Boeing 737 aircraft simulator. Highly specialized environment requiring precision engineering.
Installed a 780 square-meter roof system consisting of spray foam insulation, betkal, and a double-layer bitumen mat system for a joint IDF / USG facility.
Contracted to renovate and maintain four LC Waikiki retail stores. Project included full interior renovation, MEP updates, and ongoing maintenance support.
Contracted to replace 110 electrical light fixtures within the Consulate General of Sweden. Work completed within the consulate's operational requirements with minimal disruption.
Contracted to repair and maintain air conditioning systems at the ELAL facility in Lod, Israel. Ongoing maintenance contract ensuring operational reliability.